Project Status

Current Status Of Alisa Solar Project

  • The Alisa Solar team is currently seeking a Special Use Permit from Yuma County.
  • Our project team is working to complete Yuma County permitting by mid 2024.
  • Once permitted, construction is expected to start in 2028 with completion and operations in 2030.
  • The project will interconnect at Hassayampa – North Gila 1 & 2 500 kV transmission lines.
  • The construction haul-route to deliver supplies to the site will be designed to prioritize safety and minimize impact to traffic on roads. The team is currently evaluating various paths to ensure minimal impact.

Project timeline

Alisa solar project timeline desktopAlisa solar project timeline

Important dates

2024

2023

During 2023: Alisa Solar project team conducted additional environmental and engineering studies to mitigate project risks.

November 14: Applied for Yuma County special use permit.

2022

During 2022: Conducted environmental and engineering studies to assess site viability and continued signing agreements for the project site.

2021

During 2021: Alisa Solar project team signed agreements for the project site and began meeting with landowners and neighbors.

Have questions about the Alisa Solar project?

Want to learn more about Balanced Rock Power?

Visit our website