March 26, 2024: Yuma County Planning and zoning commission hearing
During 2023: Alisa Solar project team conducted additional environmental and engineering studies to mitigate project risks.
November 14: Applied for Yuma County special use permit.
During 2022: Conducted environmental and engineering studies to assess site viability and continued signing agreements for the project site.
During 2021: Alisa Solar project team signed agreements for the project site and began meeting with landowners and neighbors.